# Draw Review: Riverside Lofts, 1200 River Rd, Application #7

Period to 10/31/2026 · Contractor: Riverbend Builders LLC · Owner: Riverside Lofts Owner LLC  
Prepared November 20, 2026 by Dandolo Digital · **DRAFT for reviewer edit and signature**

## Summary

The contractor requests **$1,671,800.00** (G702 line 8) against a contract sum of $12,445,000.00, with $5,405,000.00 completed and stored to date (43.43%). Retainage held is $518,500.00 (effective 9.59%). The review found 21 high-severity exception(s) and 14 medium.

**Recommendation: Fund with conditions.** High-severity exceptions must be cleared or the payment reduced before funding. Payment-affecting exceptions total about **$272,000.00** (indicative, before reviewer judgment).

## Conditions to fund

1. **Item 3 Sitework & Utilities: billed beyond lender budget.** _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
2. **Item 10 HVAC: scheduled value exceeds lender budget.** _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10)_
3. **Item 3 Sitework & Utilities: billed over 100% of scheduled value.** Hold the overage until a change order or reallocation is approved. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
4. **Line 2 includes unapproved change orders.** Remove unapproved change orders from the contract sum until executed by the owner. _(Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 2; Riverside_Lofts_Draw_7_backup.pdf · p.8 · Change order)_
5. **Possible duplicate invoice from ClearView Glazing Inc.** Confirm the invoice is not billed twice. _(Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)_
6. **No lien waiver from Apex Wrecking.** Request Apex Wrecking's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 2)_
7. **No lien waiver from Ground Up Civil.** Request Ground Up Civil's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
8. **No lien waiver from Keystone Concrete.** Request Keystone Concrete's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 4)_
9. **No lien waiver from Ironclad Steel.** Request Ironclad Steel's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 5)_
10. **No lien waiver from Northside Interiors.** Request Northside Interiors's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)_
11. **No lien waiver from TopLine Roofing.** Request TopLine Roofing's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 7)_
12. **No lien waiver from Flowright Plumbing.** Request Flowright Plumbing's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 9)_
13. **No lien waiver from Bright Line Electric.** Request Bright Line Electric's conditional (current) and unconditional (prior) waivers. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 11)_
14. **G703 GRAND TOTALS — this period column does not add.** Ask for a corrected continuation sheet; confirm which figure was used to compute the payment. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)_
15. **G703 Item 6 Framing & Drywall: completed to date does not foot.** Correct the row and re-issue the continuation sheet. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)_
16. **G703 GRAND TOTALS: completed to date does not foot.** Correct the row and re-issue the continuation sheet. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)_
17. **Line 7 does not match the prior certificate.** Reconcile to amounts actually certified and paid on the prior draw. _(Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 7; Riverside_Lofts_Draw_6.pdf · p.1 · Prior G702 line 6)_
18. **Item 14 Contractor Fee: retainage released.** Confirm the release was approved; otherwise withhold. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 14; Riverside_Lofts_Draw_6.pdf · p.2 · Prior G703 item 14)_
19. **Retainage under-withheld by $22,000.00.** Confirm the retainage terms in the loan/construction contract; if 10% applies to all lines, reduce the payment by the shortfall. _(Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 5)_
20. **$85,000.00 of stored materials without support.** Request bills of sale, invoices, proof of insurance and storage location (and photos / inspection) for stored materials. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 8; Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)_
21. **Item 10 HVAC: GC bills $60,000.00 more than Summit Mechanical Inc.** Ask the GC to reconcile its line to the subcontractor's application. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10; Riverside_Lofts_Draw_7_backup.pdf · p.1 · Summit Mechanical Inc summary line 4)_

## Exceptions

### Budget

- **[HIGH] Item 3 Sitework & Utilities: billed beyond lender budget.** Completed $670,000.00 vs approved budget $640,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
- **[HIGH] Item 10 HVAC: scheduled value exceeds lender budget.** G703 $1,240,000.00 vs approved budget $1,200,000.00 ('HVAC'). _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10)_
- **[HIGH] Item 3 Sitework & Utilities: billed over 100% of scheduled value.** Completed $670,000.00 exceeds scheduled value $640,000.00 by $30,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
- **[MEDIUM] Item 16 Contingency: contingency drawn.** $30,000.00 this period, $30,000.00 to date on a contingency/allowance line. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 16)_
- **[MEDIUM] Item 10 HVAC: subcontract exceeds the budget line by $25,000.00.** Summit Mechanical Inc's contract sum to date is $1,265,000.00; the G703 line is budgeted at $1,240,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10; Riverside_Lofts_Draw_7_backup.pdf · p.1 · Summit Mechanical Inc summary line 3)_

### Change orders

- **[HIGH] Line 2 includes unapproved change orders.** Executed COs total $100,000.00; Line 2 is $145,000.00, which only ties if pending CO(s) #3 ($45,000.00) are included. _(Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 2; Riverside_Lofts_Draw_7_backup.pdf · p.8 · Change order)_
- **[MEDIUM] Change order #3 is not executed.** $45,000.00 — Storm sewer upgrade per civil revision 4. Owner signature not found / status pending. _(Riverside_Lofts_Draw_7_backup.pdf · p.8 · Change order)_

### Invoices

- **[HIGH] Possible duplicate invoice from ClearView Glazing Inc.** Invoice CV-2207 for $85,000.00 matches another invoice in the package on number. _(Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)_

### Lien waivers

- **[HIGH] No lien waiver from Apex Wrecking.** Apex Wrecking bills -$15,000.00 this period and was paid $210,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 2)_
- **[HIGH] No lien waiver from Ground Up Civil.** Ground Up Civil bills $290,000.00 this period and was paid $380,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
- **[HIGH] No lien waiver from Keystone Concrete.** Keystone Concrete bills $150,000.00 this period and was paid $1,160,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 4)_
- **[HIGH] No lien waiver from Ironclad Steel.** Ironclad Steel bills $300,000.00 this period and was paid $640,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 5)_
- **[HIGH] No lien waiver from Northside Interiors.** Northside Interiors bills $260,000.00 this period and was paid $210,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)_
- **[HIGH] No lien waiver from TopLine Roofing.** TopLine Roofing bills $120,000.00 this period and was paid $0.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 7)_
- **[HIGH] No lien waiver from Flowright Plumbing.** Flowright Plumbing bills $140,000.00 this period and was paid $150,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 9)_
- **[HIGH] No lien waiver from Bright Line Electric.** Bright Line Electric bills $160,000.00 this period and was paid $170,000.00 previously, but no waiver from them is in the package. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 11)_
- **[MEDIUM] Riverbend Builders LLC: conditional waiver amount ≠ payment due.** Waiver is for $1,672,800.00; the application shows $1,671,800.00 due this period. _(Riverside_Lofts_Draw_7_backup.pdf · p.3 · Lien waiver; Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 8)_
- **[MEDIUM] Waiver from Summit Mechanical Inc lists exceptions.** Exceptions: Disputed retention of $15,300.00 on Application 3 _(Riverside_Lofts_Draw_7_backup.pdf · p.4 · Lien waiver)_

### Math

- **[HIGH] G703 GRAND TOTALS — this period column does not add.** Rows above add to $1,752,000.00; the GRAND TOTALS row shows $1,757,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)_
- **[HIGH] G703 Item 6 Framing & Drywall: completed to date does not foot.** Previous $210,000.00 + this period $260,000.00 + stored — = $470,000.00; row shows $480,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)_
- **[HIGH] G703 GRAND TOTALS: completed to date does not foot.** Previous $3,558,000.00 + this period $1,757,000.00 + stored $85,000.00 = $5,400,000.00; row shows $5,405,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)_

### Prior draw

- **[HIGH] Line 7 does not match the prior certificate.** Less previous certificates is $3,214,700.00; prior application line 6 was $3,202,200.00. _(Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 7; Riverside_Lofts_Draw_6.pdf · p.1 · Prior G702 line 6)_
- **[MEDIUM] Item 2 Demolition: negative billing this period.** This period is -$15,000.00 against previous billings of $210,000.00. Work previously certified is being reversed or moved to another line. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 2)_

### Retainage

- **[HIGH] Item 14 Contractor Fee: retainage released.** Retainage on this line fell from $16,800.00 to $0.00 while completed work rose to $220,000.00. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 14; Riverside_Lofts_Draw_6.pdf · p.2 · Prior G703 item 14)_
- **[HIGH] Retainage under-withheld by $22,000.00.** At the stated 10.0% rate, retainage on $5,405,000.00 completed & stored should be $540,500.00; the application holds $518,500.00 (effective 9.59%). _(Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 5)_
- **[MEDIUM] No retainage held on 1 billed line(s).** $220,000.00 of completed work carries $0 retainage while other lines are retained: Item 14 Contractor Fee ($220,000.00). _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 14)_

### Stored materials

- **[HIGH] $85,000.00 of stored materials without support.** 1 line(s) bill materials stored but not installed; no bill of sale, storage agreement or insurance for them was found in the package. Only invoice(s) were found (ClearView Glazing Inc CV-2207, ClearView Glazing Inc CV-2207); an invoice alone doesn't show title, location or insurance. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 8; Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)_

### Sub pay apps

- **[HIGH] Item 10 HVAC: GC bills $60,000.00 more than Summit Mechanical Inc.** G703 completed to date $400,000.00 vs Summit Mechanical Inc application #4 (10/31/26) $340,000.00. The GC is billing ahead of its subcontractor. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10; Riverside_Lofts_Draw_7_backup.pdf · p.1 · Summit Mechanical Inc summary line 4)_
- **[MEDIUM] Item 3 Sitework & Utilities: no Ground Up Civil application in package.** The GC bills $290,000.00 this period on a line performed by Ground Up Civil, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)_
- **[MEDIUM] Item 4 Concrete: no Keystone Concrete application in package.** The GC bills $150,000.00 this period on a line performed by Keystone Concrete, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 4)_
- **[MEDIUM] Item 5 Structural Steel: no Ironclad Steel application in package.** The GC bills $300,000.00 this period on a line performed by Ironclad Steel, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 5)_
- **[MEDIUM] Item 6 Framing & Drywall: no Northside Interiors application in package.** The GC bills $260,000.00 this period on a line performed by Northside Interiors, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)_
- **[MEDIUM] Item 7 Roofing: no TopLine Roofing application in package.** The GC bills $120,000.00 this period on a line performed by TopLine Roofing, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 7)_
- **[MEDIUM] Item 9 Plumbing: no Flowright Plumbing application in package.** The GC bills $140,000.00 this period on a line performed by Flowright Plumbing, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 9)_
- **[MEDIUM] Item 11 Electrical: no Bright Line Electric application in package.** The GC bills $160,000.00 this period on a line performed by Bright Line Electric, but no matching sub application was found. _(Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 11)_

## Verified and in order

- G702 lines 3, 5, 6, 8 and 9 foot.
- G702 lines 3, 4 and 5 tie to the G703 totals.
- The G703 'from previous application' column ties to the prior draw's completed to date.

## Open questions for the borrower / GC

- Confirm owner/lender approval of each contingency use. (Item 16 Contingency: contingency drawn)
- Ask how the buyout overrun is funded (contingency, reallocation or borrower equity). (Item 10 HVAC: subcontract exceeds the budget line by $25,000.00)
- Do not fund work under this change order until it is executed. (Change order #3 is not executed)
- Review the excepted amounts before funding. (Waiver from Summit Mechanical Inc lists exceptions)
- Ask the GC why previously certified work is being reversed and where it was re-billed. (Item 2 Demolition: negative billing this period)
- Confirm these lines are contractually exempt from retainage (e.g. fee, GCs, insurance) or withhold. (No retainage held on 1 billed line(s))
- Request Ground Up Civil's application for this period. (Item 3 Sitework & Utilities: no Ground Up Civil application in package)
- Request Keystone Concrete's application for this period. (Item 4 Concrete: no Keystone Concrete application in package)
- Request Ironclad Steel's application for this period. (Item 5 Structural Steel: no Ironclad Steel application in package)
- Request Northside Interiors's application for this period. (Item 6 Framing & Drywall: no Northside Interiors application in package)
- Request TopLine Roofing's application for this period. (Item 7 Roofing: no TopLine Roofing application in package)
- Request Flowright Plumbing's application for this period. (Item 9 Plumbing: no Flowright Plumbing application in package)
- Request Bright Line Electric's application for this period. (Item 11 Electrical: no Bright Line Electric application in package)

## Documents reviewed

- Riverside_Lofts_Draw_7.pdf: 2 pages (1 g702, 1 g703)
- Riverside_Lofts_Draw_7_backup.pdf: 10 pages (1 sub summary, 1 sub detail, 3 lien waiver, 3 change order, 2 invoice)
- Prior draw: Riverside_Lofts_Draw_6.pdf (2 pages)

_Automated tie-outs and exception screening; findings should be verified against the source pages before funding._