Draw 7 · Application #7
| Item | Description | Sub | Scheduled | Previous | This period | Stored | Completed | % | Balance | Retainage | Flags |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | General Conditions | $820,000.00 | $205,000.00 | $45,000.00 | $250,000.00 | 30.49% | $570,000.00 | $25,000.00 | p.2 | ||
| 2 | Demolition | Apex Wrecking | $210,000.00 | $210,000.00 | -$15,000.00 | $195,000.00 | 92.86% | $15,000.00 | $19,500.00 | p.2 | |
| 3 | Sitework & Utilities | Ground Up Civil | $640,000.00 | $380,000.00 | $290,000.00 | $670,000.00 | 104.69% | -$30,000.00 | $67,000.00 | p.2 | |
| 4 | Concrete | Keystone Concrete | $1,450,000.00 | $1,160,000.00 | $150,000.00 | $1,310,000.00 | 90.34% | $140,000.00 | $131,000.00 | p.2 | |
| 5 | Structural Steel | Ironclad Steel | $1,180,000.00 | $640,000.00 | $300,000.00 | $940,000.00 | 79.66% | $240,000.00 | $94,000.00 | p.2 | |
| 6 | Framing & Drywall | Northside Interiors | $1,320,000.00 | $210,000.00 | $260,000.00 | $480,000.00 | 36.36% | $840,000.00 | $48,000.00 | p.2 | |
| 7 | Roofing | TopLine Roofing | $410,000.00 | $0.00 | $120,000.00 | $120,000.00 | 29.27% | $290,000.00 | $12,000.00 | p.2 | |
| 8 | Windows & Storefront | ClearView Glazing | $760,000.00 | $0.00 | $0.00 | $85,000.00 | $85,000.00 | 11.18% | $675,000.00 | $8,500.00 | p.2 |
| 9 | Plumbing | Flowright Plumbing | $980,000.00 | $150,000.00 | $140,000.00 | $290,000.00 | 29.59% | $690,000.00 | $29,000.00 | p.2 | |
| 10 | HVAC | Summit Mechanical | $1,240,000.00 | $180,000.00 | $220,000.00 | $400,000.00 | 32.26% | $840,000.00 | $40,000.00 | p.2 | |
| 11 | Electrical | Bright Line Electric | $1,150,000.00 | $170,000.00 | $160,000.00 | $330,000.00 | 28.70% | $820,000.00 | $33,000.00 | p.2 | |
| 12 | Interior Finishes | $890,000.00 | $0.00 | $0.00 | $0.00 | 0.00% | $890,000.00 | $0.00 | p.2 | ||
| 13 | Elevators | Vertex Elevator | $420,000.00 | $0.00 | $0.00 | $0.00 | 0.00% | $420,000.00 | $0.00 | p.2 | |
| 14 | Contractor Fee | $560,000.00 | $168,000.00 | $52,000.00 | $220,000.00 | 39.29% | $340,000.00 | $0.00 | p.2 | ||
| 15 | Insurance & Bonds | $170,000.00 | $85,000.00 | $0.00 | $85,000.00 | 50.00% | $85,000.00 | $8,500.00 | p.2 | ||
| 16 | Contingency | $200,000.00 | $0.00 | $30,000.00 | $30,000.00 | 15.00% | $170,000.00 | $3,000.00 | p.2 | ||
| 17 | CO #3 Storm sewer upgrade | Ground Up Civil | $45,000.00 | $0.00 | $0.00 | $0.00 | 0.00% | $45,000.00 | $0.00 | p.2 | |
| GRAND TOTALS | $12,445,000.00 | $3,558,000.00 | $1,757,000.00 | $85,000.00 | $5,405,000.00 | 43.43% | $7,040,000.00 | $518,500.00 | p.2 |
Rows with a colored dot carry an exception (hover for the title). Page links open the source PDF at that page.
Application summary
| 1. Original contract sum | $12,300,000.00 |
| 2. Net change by change orders | $145,000.00 |
| 3. Contract sum to date | $12,445,000.00 |
| 4. Total completed & stored to date | $5,405,000.00 |
| 5a. Retainage on completed work (10%) | $518,500.00 |
| 5b. Retainage on stored material | — |
| 5. Total retainage | $518,500.00 |
| 6. Total earned less retainage | $4,886,500.00 |
| 7. Less previous certificates | $3,214,700.00 |
| 8. Current payment due | $1,671,800.00 |
| 9. Balance to finish incl. retainage | $7,558,500.00 |
| Amount certified (architect) | — |
Header
| Project | Riverside Lofts, 1200 River Rd |
| Owner | Riverside Lofts Owner LLC |
| Contractor | Riverbend Builders LLC |
| Contract for | Multifamily new construction |
| Application # | 7 |
| Application date | 10/31/2026 |
| Period to | 10/31/2026 |
| Change orders (prev add / ded) | $100,000.00 / $0.00 |
| Change orders (this month add / ded) | $45,000.00 / $0.00 |
| Subcontractor | Scope | App # | Period to | Contract | Completed | Retainage | Due | G703 line | GC line completed | Signed |
|---|---|---|---|---|---|---|---|---|---|---|
| Summit Mechanical Inc | HVAC | 4 | 10/31/26 | $1,265,000.00 | $340,000.00 | $34,000.00 | $144,000.00 | Item 10 HVAC | $400,000.00 | n/a |
Each current line matched to the prior draw's line by description, item number and the previous-billing column. Unmatched lines are new, renamed or dropped.
| This draw | Prior draw | Match | Prior scheduled | Scheduled now | Prior completed | Previous (now) | Completed now | Flag |
|---|---|---|---|---|---|---|---|---|
| Item 1 General Conditions | Item 1 General Conditions | 1.35 | $820,000.00 | $820,000.00 | $205,000.00 | $205,000.00 | $250,000.00 | |
| Item 2 Demolition | Item 2 Demolition | 1.35 | $210,000.00 | $210,000.00 | $210,000.00 | $210,000.00 | $195,000.00 | completed went down |
| Item 3 Sitework & Utilities | Item 3 Sitework & Utilities | 1.35 | $640,000.00 | $640,000.00 | $380,000.00 | $380,000.00 | $670,000.00 | |
| Item 4 Concrete | Item 4 Concrete | 1.35 | $1,450,000.00 | $1,450,000.00 | $1,160,000.00 | $1,160,000.00 | $1,310,000.00 | |
| Item 5 Structural Steel | Item 5 Structural Steel | 1.35 | $1,180,000.00 | $1,180,000.00 | $640,000.00 | $640,000.00 | $940,000.00 | |
| Item 6 Framing & Drywall | Item 6 Framing & Drywall | 1.35 | $1,320,000.00 | $1,320,000.00 | $210,000.00 | $210,000.00 | $480,000.00 | |
| Item 7 Roofing | Item 7 Roofing | 1.1 | $410,000.00 | $410,000.00 | $0.00 | $0.00 | $120,000.00 | |
| Item 8 Windows & Storefront | Item 8 Windows & Storefront | 1.1 | $760,000.00 | $760,000.00 | $0.00 | $0.00 | $85,000.00 | |
| Item 9 Plumbing | Item 9 Plumbing | 1.35 | $980,000.00 | $980,000.00 | $150,000.00 | $150,000.00 | $290,000.00 | |
| Item 10 HVAC | Item 10 HVAC | 1.35 | $1,240,000.00 | $1,240,000.00 | $180,000.00 | $180,000.00 | $400,000.00 | |
| Item 11 Electrical | Item 11 Electrical | 1.35 | $1,150,000.00 | $1,150,000.00 | $170,000.00 | $170,000.00 | $330,000.00 | |
| Item 12 Interior Finishes | Item 12 Interior Finishes | 1.1 | $890,000.00 | $890,000.00 | $0.00 | $0.00 | $0.00 | |
| Item 13 Elevators | Item 13 Elevators | 1.1 | $420,000.00 | $420,000.00 | $0.00 | $0.00 | $0.00 | |
| Item 14 Contractor Fee | Item 14 Contractor Fee | 1.35 | $560,000.00 | $560,000.00 | $168,000.00 | $168,000.00 | $220,000.00 | retainage released |
| Item 15 Insurance & Bonds | Item 15 Insurance & Bonds | 1.35 | $170,000.00 | $170,000.00 | $85,000.00 | $85,000.00 | $85,000.00 | |
| Item 16 Contingency | Item 16 Contingency | 1.1 | $200,000.00 | $200,000.00 | $0.00 | $0.00 | $30,000.00 | |
| Item 17 CO #3 Storm sewer upgrade | — | — | $45,000.00 | — | $0.00 | $0.00 | new line |
| File | Page | Classified as | Read by | Text layer |
|---|---|---|---|---|
| Riverside_Lofts_Draw_7.pdf | p.1 | g702 | rules | yes |
| Riverside_Lofts_Draw_7.pdf | p.2 | g703 | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.1 | sub summary | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.2 | sub detail | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.3 | lien waiver | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.4 | lien waiver | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.5 | lien waiver | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.6 | change order | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.7 | change order | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.8 | change order | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.9 | invoice | rules | yes |
| Riverside_Lofts_Draw_7_backup.pdf | p.10 | invoice | rules | yes |
Draw Review: Riverside Lofts, 1200 River Rd, Application #7
Period to 10/31/2026 · Contractor: Riverbend Builders LLC · Owner: Riverside Lofts Owner LLC
Prepared November 20, 2026 by Dandolo Digital · DRAFT for reviewer edit and signature
Summary
The contractor requests $1,671,800.00 (G702 line 8) against a contract sum of $12,445,000.00, with $5,405,000.00 completed and stored to date (43.43%). Retainage held is $518,500.00 (effective 9.59%). The review found 21 high-severity exception(s) and 14 medium.
Recommendation: Fund with conditions. High-severity exceptions must be cleared or the payment reduced before funding. Payment-affecting exceptions total about $272,000.00 (indicative, before reviewer judgment).
Conditions to fund
- Item 3 Sitework & Utilities: billed beyond lender budget. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- Item 10 HVAC: scheduled value exceeds lender budget. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10)
- Item 3 Sitework & Utilities: billed over 100% of scheduled value. Hold the overage until a change order or reallocation is approved. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- Line 2 includes unapproved change orders. Remove unapproved change orders from the contract sum until executed by the owner. (Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 2; Riverside_Lofts_Draw_7_backup.pdf · p.8 · Change order)
- Possible duplicate invoice from ClearView Glazing Inc. Confirm the invoice is not billed twice. (Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)
- No lien waiver from Apex Wrecking. Request Apex Wrecking's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 2)
- No lien waiver from Ground Up Civil. Request Ground Up Civil's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- No lien waiver from Keystone Concrete. Request Keystone Concrete's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 4)
- No lien waiver from Ironclad Steel. Request Ironclad Steel's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 5)
- No lien waiver from Northside Interiors. Request Northside Interiors's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)
- No lien waiver from TopLine Roofing. Request TopLine Roofing's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 7)
- No lien waiver from Flowright Plumbing. Request Flowright Plumbing's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 9)
- No lien waiver from Bright Line Electric. Request Bright Line Electric's conditional (current) and unconditional (prior) waivers. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 11)
- G703 GRAND TOTALS — this period column does not add. Ask for a corrected continuation sheet; confirm which figure was used to compute the payment. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)
- G703 Item 6 Framing & Drywall: completed to date does not foot. Correct the row and re-issue the continuation sheet. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)
- G703 GRAND TOTALS: completed to date does not foot. Correct the row and re-issue the continuation sheet. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)
- Line 7 does not match the prior certificate. Reconcile to amounts actually certified and paid on the prior draw. (Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 7; Riverside_Lofts_Draw_6.pdf · p.1 · Prior G702 line 6)
- Item 14 Contractor Fee: retainage released. Confirm the release was approved; otherwise withhold. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 14; Riverside_Lofts_Draw_6.pdf · p.2 · Prior G703 item 14)
- Retainage under-withheld by $22,000.00. Confirm the retainage terms in the loan/construction contract; if 10% applies to all lines, reduce the payment by the shortfall. (Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 5)
- $85,000.00 of stored materials without support. Request bills of sale, invoices, proof of insurance and storage location (and photos / inspection) for stored materials. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 8; Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)
- Item 10 HVAC: GC bills $60,000.00 more than Summit Mechanical Inc. Ask the GC to reconcile its line to the subcontractor's application. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10; Riverside_Lofts_Draw_7_backup.pdf · p.1 · Summit Mechanical Inc summary line 4)
Exceptions
Budget
- [HIGH] Item 3 Sitework & Utilities: billed beyond lender budget. Completed $670,000.00 vs approved budget $640,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- [HIGH] Item 10 HVAC: scheduled value exceeds lender budget. G703 $1,240,000.00 vs approved budget $1,200,000.00 ('HVAC'). (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10)
- [HIGH] Item 3 Sitework & Utilities: billed over 100% of scheduled value. Completed $670,000.00 exceeds scheduled value $640,000.00 by $30,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- [MEDIUM] Item 16 Contingency: contingency drawn. $30,000.00 this period, $30,000.00 to date on a contingency/allowance line. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 16)
- [MEDIUM] Item 10 HVAC: subcontract exceeds the budget line by $25,000.00. Summit Mechanical Inc's contract sum to date is $1,265,000.00; the G703 line is budgeted at $1,240,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10; Riverside_Lofts_Draw_7_backup.pdf · p.1 · Summit Mechanical Inc summary line 3)
Change orders
- [HIGH] Line 2 includes unapproved change orders. Executed COs total $100,000.00; Line 2 is $145,000.00, which only ties if pending CO(s) #3 ($45,000.00) are included. (Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 2; Riverside_Lofts_Draw_7_backup.pdf · p.8 · Change order)
- [MEDIUM] Change order #3 is not executed. $45,000.00 — Storm sewer upgrade per civil revision 4. Owner signature not found / status pending. (Riverside_Lofts_Draw_7_backup.pdf · p.8 · Change order)
Invoices
- [HIGH] Possible duplicate invoice from ClearView Glazing Inc. Invoice CV-2207 for $85,000.00 matches another invoice in the package on number. (Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)
Lien waivers
- [HIGH] No lien waiver from Apex Wrecking. Apex Wrecking bills -$15,000.00 this period and was paid $210,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 2)
- [HIGH] No lien waiver from Ground Up Civil. Ground Up Civil bills $290,000.00 this period and was paid $380,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- [HIGH] No lien waiver from Keystone Concrete. Keystone Concrete bills $150,000.00 this period and was paid $1,160,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 4)
- [HIGH] No lien waiver from Ironclad Steel. Ironclad Steel bills $300,000.00 this period and was paid $640,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 5)
- [HIGH] No lien waiver from Northside Interiors. Northside Interiors bills $260,000.00 this period and was paid $210,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)
- [HIGH] No lien waiver from TopLine Roofing. TopLine Roofing bills $120,000.00 this period and was paid $0.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 7)
- [HIGH] No lien waiver from Flowright Plumbing. Flowright Plumbing bills $140,000.00 this period and was paid $150,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 9)
- [HIGH] No lien waiver from Bright Line Electric. Bright Line Electric bills $160,000.00 this period and was paid $170,000.00 previously, but no waiver from them is in the package. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 11)
- [MEDIUM] Riverbend Builders LLC: conditional waiver amount ≠ payment due. Waiver is for $1,672,800.00; the application shows $1,671,800.00 due this period. (Riverside_Lofts_Draw_7_backup.pdf · p.3 · Lien waiver; Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 8)
- [MEDIUM] Waiver from Summit Mechanical Inc lists exceptions. Exceptions: Disputed retention of $15,300.00 on Application 3 (Riverside_Lofts_Draw_7_backup.pdf · p.4 · Lien waiver)
Math
- [HIGH] G703 GRAND TOTALS — this period column does not add. Rows above add to $1,752,000.00; the GRAND TOTALS row shows $1,757,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)
- [HIGH] G703 Item 6 Framing & Drywall: completed to date does not foot. Previous $210,000.00 + this period $260,000.00 + stored — = $470,000.00; row shows $480,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)
- [HIGH] G703 GRAND TOTALS: completed to date does not foot. Previous $3,558,000.00 + this period $1,757,000.00 + stored $85,000.00 = $5,400,000.00; row shows $5,405,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 GRAND TOTALS)
Prior draw
- [HIGH] Line 7 does not match the prior certificate. Less previous certificates is $3,214,700.00; prior application line 6 was $3,202,200.00. (Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 7; Riverside_Lofts_Draw_6.pdf · p.1 · Prior G702 line 6)
- [MEDIUM] Item 2 Demolition: negative billing this period. This period is -$15,000.00 against previous billings of $210,000.00. Work previously certified is being reversed or moved to another line. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 2)
Retainage
- [HIGH] Item 14 Contractor Fee: retainage released. Retainage on this line fell from $16,800.00 to $0.00 while completed work rose to $220,000.00. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 14; Riverside_Lofts_Draw_6.pdf · p.2 · Prior G703 item 14)
- [HIGH] Retainage under-withheld by $22,000.00. At the stated 10.0% rate, retainage on $5,405,000.00 completed & stored should be $540,500.00; the application holds $518,500.00 (effective 9.59%). (Riverside_Lofts_Draw_7.pdf · p.1 · G702 line 5)
- [MEDIUM] No retainage held on 1 billed line(s). $220,000.00 of completed work carries $0 retainage while other lines are retained: Item 14 Contractor Fee ($220,000.00). (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 14)
Stored materials
- [HIGH] $85,000.00 of stored materials without support. 1 line(s) bill materials stored but not installed; no bill of sale, storage agreement or insurance for them was found in the package. Only invoice(s) were found (ClearView Glazing Inc CV-2207, ClearView Glazing Inc CV-2207); an invoice alone doesn't show title, location or insurance. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 8; Riverside_Lofts_Draw_7_backup.pdf · p.9 · Invoice; Riverside_Lofts_Draw_7_backup.pdf · p.10 · Invoice)
Sub pay apps
- [HIGH] Item 10 HVAC: GC bills $60,000.00 more than Summit Mechanical Inc. G703 completed to date $400,000.00 vs Summit Mechanical Inc application #4 (10/31/26) $340,000.00. The GC is billing ahead of its subcontractor. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 10; Riverside_Lofts_Draw_7_backup.pdf · p.1 · Summit Mechanical Inc summary line 4)
- [MEDIUM] Item 3 Sitework & Utilities: no Ground Up Civil application in package. The GC bills $290,000.00 this period on a line performed by Ground Up Civil, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 3)
- [MEDIUM] Item 4 Concrete: no Keystone Concrete application in package. The GC bills $150,000.00 this period on a line performed by Keystone Concrete, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 4)
- [MEDIUM] Item 5 Structural Steel: no Ironclad Steel application in package. The GC bills $300,000.00 this period on a line performed by Ironclad Steel, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 5)
- [MEDIUM] Item 6 Framing & Drywall: no Northside Interiors application in package. The GC bills $260,000.00 this period on a line performed by Northside Interiors, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 6)
- [MEDIUM] Item 7 Roofing: no TopLine Roofing application in package. The GC bills $120,000.00 this period on a line performed by TopLine Roofing, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 7)
- [MEDIUM] Item 9 Plumbing: no Flowright Plumbing application in package. The GC bills $140,000.00 this period on a line performed by Flowright Plumbing, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 9)
- [MEDIUM] Item 11 Electrical: no Bright Line Electric application in package. The GC bills $160,000.00 this period on a line performed by Bright Line Electric, but no matching sub application was found. (Riverside_Lofts_Draw_7.pdf · p.2 · G703 item 11)
Verified and in order
- G702 lines 3, 5, 6, 8 and 9 foot.
- G702 lines 3, 4 and 5 tie to the G703 totals.
- The G703 'from previous application' column ties to the prior draw's completed to date.
Open questions for the borrower / GC
- Confirm owner/lender approval of each contingency use. (Item 16 Contingency: contingency drawn)
- Ask how the buyout overrun is funded (contingency, reallocation or borrower equity). (Item 10 HVAC: subcontract exceeds the budget line by $25,000.00)
- Do not fund work under this change order until it is executed. (Change order #3 is not executed)
- Review the excepted amounts before funding. (Waiver from Summit Mechanical Inc lists exceptions)
- Ask the GC why previously certified work is being reversed and where it was re-billed. (Item 2 Demolition: negative billing this period)
- Confirm these lines are contractually exempt from retainage (e.g. fee, GCs, insurance) or withhold. (No retainage held on 1 billed line(s))
- Request Ground Up Civil's application for this period. (Item 3 Sitework & Utilities: no Ground Up Civil application in package)
- Request Keystone Concrete's application for this period. (Item 4 Concrete: no Keystone Concrete application in package)
- Request Ironclad Steel's application for this period. (Item 5 Structural Steel: no Ironclad Steel application in package)
- Request Northside Interiors's application for this period. (Item 6 Framing & Drywall: no Northside Interiors application in package)
- Request TopLine Roofing's application for this period. (Item 7 Roofing: no TopLine Roofing application in package)
- Request Flowright Plumbing's application for this period. (Item 9 Plumbing: no Flowright Plumbing application in package)
- Request Bright Line Electric's application for this period. (Item 11 Electrical: no Bright Line Electric application in package)
Documents reviewed
- Riverside_Lofts_Draw_7.pdf: 2 pages (1 g702, 1 g703)
- Riverside_Lofts_Draw_7_backup.pdf: 10 pages (1 sub summary, 1 sub detail, 3 lien waiver, 3 change order, 2 invoice)
- Prior draw: Riverside_Lofts_Draw_6.pdf (2 pages)
Automated tie-outs and exception screening; findings should be verified against the source pages before funding.